Executive Summary
Industry Experience : field supervisor with 10 years of comprehensive knowledge of utility scele power plant startup, normal operation,and transient response action. Zero lost time to injury or accident.
Key Achievement
- Emergency handle while fire in turbine compartment.
- Black out restoration with 1 hour machine started and synch with grid.
- GE Frame 9E DLN/9E Gas turbine power plant Commissioning and start up & shutdown.
- ABB Frame 131 DM Gas turbine power plant Commissioning and start up& shutdown.
- SEIMENS STG 800 Gas turbine powers plant Commissioning and start up & shutdown.
Career History
Company: Anton Oil

Plant and Location: BUZURGAN POWER PLANT 200 MW IRAQ (SIEMENS STGT 800)
Responsibility: CCR OPERATOR
Serving: 01 JANUARY 2019 UP TO DATE
- 4 Gas Turbines (duel fuel) of 200 MW, SIEMANS model SGT 800 with PCS7 control system.
- Ensure smooth operation, safe startup / shut down of Power Plant during the shift.
- Ensure smooth operation, safe startup / shut down of GAS compressor.
- Safe startup / shut down of GAS compressor nitrogen generator.
- Records all plant/auxiliary equipment operating data, including alarms and protective devices that are actuated and report any deviation to Shift supervisor for necessary action.
- Performs mechanical and electrical, manual equipment isolation.
- Troubleshoot operational problems and initiate maintenance requests.
- Online and off line washing of gas turbine using GE chemicals.
- Day to day plant operation, safely and efficiently, according to good utility practice, dispatch instructions, the company rules and procedures ,MOE guidelines, legal ,environmental, contractual and other requirements.
- Perform other duties related to operations including assisting with maintenance planning and coordination, training of operators, investigating loss events, and developing and reviewing procedures.
- Development of short and long term operation strategy for the plant and the development of a capable shift engineer and operator team to support that strategy.
- Ensure that plant meets safety, availability, reliability, efficiency, generation and budget targets.
Company: Qaiwan Group

Plant and Location: BAZEYAN POWER PLANT BCCPP 750 MW IRAQ (GE FRAME 9E GT)
Responsibility: FIELD SUPERVISOR
Serving: 22 MAY /2016 TO 34 DEC / 2018
- 4 Gas Turbines (duel fuel) of 125 MW, GE model 9E with DLN MARK 6e control system.
- Ensure smooth operation, safe startup / shut down of Power Plant during the shift.
- Records all plant/auxiliary equipment operating data, including alarms and protective devices that are, actuated and report any deviation to Shift supervisor for necessary action.
- Performs mechanical and electrical, manual equipment isolation.
- Troubleshoot operational problems and initiate maintenance requests.
- Online and off line washing of gas turbine using GE chemicals.
- Day to day plant operation, safely and efficiently, according to good utility practice, dispatch instructions, the company rules and procedures ,MOE guidelines, legal ,environmental, contractual and other requirements
- 2 BSDG (2500KVA) for blackout backup of the plant…
- Perform other duties related to operations including assisting with maintenance planning and coordination, training of operators, investigating loss events, and developing and reviewing procedures.
- Development of short and long term operation strategy for the plant and the development of a capable shift engineer and operator team to support that strategy.
- Assist to establish the appropriate procedure and computerized maintenance management processes as applicable to a prudent operation management, in particular the permit to work system
Company: ProDiesel

Plant and Location: ALSHOIBA 185 MW POWE PLANT IRAQ (ABB 131DM GT)
Responsibility: FIELD OPERATOR
Serving: JAN-12-2016 TO MAY 1-2017
- 1*2 Gas Turbines (duel fuel) of 100MW. ABB 131-DM Gas Turbine with mark V control system
- Water injection system With Combustion system
- 132kv AIS Double bus Switch yard system with ABB control
- ESD 16 V-cylinder BSDG (2500KVA) for blackout backup of the plant
- Ensure smooth operation, safe startup / shut down of Power Plant during the shift.
- Responsible for fire of GT Synchronization test with grid.
- Identify Abnormalities in routine operation of the plant equipment and informing to CRO.
- Perform monitoring and adjustments of Generator set parameters for the satisfactory Operation of the units.
- Monitor and adjust vital Generator set parameters (i.e. kW, Amp, KVAR, P.F etc.) for the satisfactory operation of the units.
Company: PetroChina

Plant and Location: HALFAYA OIL FIELD 29MW POWER PLANT IRAQ (STGT 300)
Responsibility: FIELD OPERATOR
Serving: FROM- AUG-2014 to January 2016
- 1*3 unit 7.90mw Siemens gas turbine STGT 300 with dual fuel mode with Siemens SIMATIC PLC Control.
- 1 CAT Black start generator with 1.5Mw capacity for emergency startup of gas turbine Duties and Responsibilities
ensure smooth operation, safe start-up / shut down of Power Plant during the shift. - 1 CAT Black start generator with 1.5Mw capacity for emergency startup of gas turbine Duties and Responsibilities
- Ensure smooth operation, safe start-up / shut down of Power Plant during the shift.
- Identify abnormalities in routine operation of the plant equipment and informing to Control room operator
- Perform monitoring and adjustments of turbine set parameters for the satisfactory Operation of the units.
- Perform the job assigned in a timely and accurate manner; develop the initiative to learn and perform the Electrical and Mechanical skills independently and with confidence.
Company: Albario

Plant and Location: KARBALA POWER PLANT 250MW IRAQ (GE FRAME 9E GT)
Responsibility: FIELD OPERATOR
Serving: FROM JULY 2013 – Nov 2014
- Gas Turbines (duel fuel) of 125MW, GE model 9001E with DLN 2.6 control system
- Water injection system
- 132kv Double bus bar GIS Switch yard system
- BSDG (5500KVA)for blackout backup of the plant
Responsible for the proper and efficient operation of gas turbine and its auxiliaries - Proficient at operating the plant via a remote distributed control system (DCS). Periodically, equipment may need to be operated locally via PLC panel interfaces.
- Performs mechanical and electrical equipment isolation
- Records all plant/auxiliary equipment operating data, including alarms and protective devices that are actuated and report any deviation to Shift supervisor for necessary action
- Start-up of black start diesel generator in the emergency condition or black out.
Company: KEPCO KPS

Plant and Location: KPS 175MW CCPP KPS PAKISTAN May 2009 to march 2013
Responsibility: Trainee OPERATOR
- Gas Turbine model Frame 9e (125MW) with respective auxiliaries,
- Steam Turbine Fuji (65MW) with respective auxiliaries,
- Dual Pressure HRSG forced circulation made by CMI.
- To perform Safe Startup, Shutdown and normal Operation of Plant having.
- Read the log book, check all the parameters of plant,
- Reporting to Sr. Shift Charge Engineer for any abnormality or change in parameters,
- Routine inspection of automation rooms and switch gear rooms
- Prepare equipment’s for maintenance activities such as electric isolation, manual isolation, Depressurization and draining.
Academic Qualification:
Diploma of Associate, Engineering (ELECTRICAL) in 2000 to 2003 from S.T.B Karachi with 1st DivisionMetric with Science in 2000
safety& training:
- Fire Fighting
- Work Permit Procedure
- Evacuation and Emergency Drill
- Emergency response plane (ERT member)
- ABB training For 6.6KV switching& 132 KV/220KV AIS switchyard
Key Skills:
- Standard start up techniques
- Component test procedure
- Environmental compliance
- Start-up and operating services methods
- Regulatory standards
- Process mastery
- Walk down of system
- Quality standards
- Maintenance and/or operating procedures
Key Achievements:
- Emergency handle while fire in turbine compartment.
- Black out restoration with 1 hour machine started and synch with grid.
- GE Frame 9E DLN/9E Gas turbine power plant Commissioning and start up & shutdown.
- ABB Frame 131 DM Gas turbine power plant Commissioning and start up& shutdown.
- SEIMENS STG 800 Gas turbine powers plant Commissioning and start up & shutdown.
Core Competencies:
- Control power-generating equipment which may use any one type of fuel, such as LDO.HFO GAS fuel.
- Read charts, meters, and gauges to monitor voltage and electricity parameter.
- Check equipment and indicators to detect evidence of operating problem.
- Adjust controls to regulate the flow of power.
- Start or stop generators, turbines, and other equipment as necessary.
- Communication with (MOE) regards Load variation, Synchronization, electrical bus change over.
- Operate BOP system via DCS or ABB control system.
- Performs Switching 132/220 kV AIS switchyard ABB / SIEMENS / CHNERIDER / GE Electric.
- Performs Switching 33/11 kV AIS switchyard ABB / SIEMENS / CHNERIDER / GE Electric
- Performs Switching 6.6 kV MCC room ABB / SIEMENS / CHNERIDER / GE Electric
- Performs switching 0.4 kV MCC switch room.
SYED MUHAMMAD BAKER SHAH
Email ID- syedbakershah@gmail.com
(Iraq)- 00964-7819706468
(Pak)- 0092-3003096270