First new coal-fired plant with carbon capture proposed by Tenaska

Tenaska Inc. is developing a site near Sweetwater, Texas, for a new 765-MW gross, 600-MW net supercritical coal-fired power plant that will capture up to 90% of the CO2 in the stack gas. The captured CO2 will to be used in enhancing oil production in the Permian Basin. The proposed construction site for the $3 billion Trailblazer Energy Center is a 1,919-acre tract east of Sweetwater and north of Interstate 20 in Nolan County. Construction could begin in late 2009 and be completed in 2014 (Figure 1).