Integrated Technologies that Enhance Power Plant Operating Flexibility

Integrated Technologies that Enhance Power Plant Operating Flexibility
Michael McManus, David Boyce, Raymond Baumgartner,
Siemens Power Generation POWER-GEN International 2007 (Source: Siemens Energy)

Abstract
The US electric power industry has changed dramatically since the downturn of the gas-turbine-based market in the early 2000’s. In the years prior to this, nearly all combined-cycle plants were planned, permitted and built with the expectation to be operated predominantly in base load. With the addition of excess generating capacity in the industry coupled with rising natural gas prices, many of the new plants had to address a new set of challenges posed by nightly and weekend shutdowns and subsequent fast start-up requirements to remain economically viable. These same challenges will be imposed on new natural gas-fired units in the foreseeable future.

To enhance the value of the new power generation assets, the US market will require these new power plants to provide a much higher level of operating flexibility, including the following needs:

• Built to span from continuous- to intermediate-duty operation
• High efficiency to maximize generation opportunities
• Rapid start to react to market opportunities
• Lower start-up emissions
• Lower operating costs (high start efficiency)
• Lower demineralized water consumption Siemens has developed highly integrated power plant solutions that offer reliable rapid start and cycling flexibility without compromising efficiency.

This paper discusses proven technologies that have been integrated to permit F-class gas turbines in combined-cycle plants to be brought to 150 MW load in as short as 10 minutes and bottoming cycles that can be brought to full load in less than half the times of their predecessors. It will also address results of testing in operating power plants that incorporate these integrated components and systems.

Introduction
Development of the gas-turbine based market in the U.S. illustrates the classic boom-bust cycle in the electric power generation industry. As shown in Figure 1, the Public Utilities Regulation Policy Act (PURPA) passed in late 1978 consequently led to a small boom of natural gas-fired generation capacity additions from the mid-1980’s through the mid-1990’s. During this 10-year period, gas-turbine based additions accounted for roughly half of the total power generation installed in the U.S. During the same time period however, total power generation additions significantly dropped to a fraction of the historical level of 20 to 30 GW per annum. This trend bottomed in 1998, when only 3 GW of total capacity were added (only 0.8 GW of which was gas-turbine based).

integrated components and systems

This prolonged lull in building power generation set the stage for what occurred from 1999 through 2005, when more than 200 GW of gas-turbine-based capacity were added. Low reserve margins caused widespread concern in numerous areas throughout the U.S. to add generation as quickly as possible. With natural gas pricing of approx. $2 per mm BTU during the timeframe that this capacity was being planned and ordered, gas-turbine based technology best satisfied this need, as either simple-cycle or combined-cycle power plants.

To read more Download PDF from Siemens

Leave a Reply

Advertise Here!

Advertise Here!

Archives

RSS Renewable Energy News From Powermag

  • Venezuela's Power System on Brink of Collapse March 1, 2010
    Venezuela, a country that relies on hydropower for almost three-quarters of its electricity, has been battling a deepening electricity crisis since a drought in 2009 and a sudden 7% surge in demand brought the country’s power system to the brink of collapse.... […]
  • Peru: The Potential to Become a Regional Energy Hub March 1, 2010
    Water and gas provide the energy for Peru’s power generation sector, and the country could generate considerably more, especially from hydro and wind. While the nation strives to extend electricity service to all its citizens, it’s also looking beyond its borders for potential future customers.... […]
  • Ethiopia's New Hydro Plant Boosts Region's Generating Capacity March 1, 2010
    Ethiopia in mid-January officially inaugurated the 420-MW Gilgel Gibe II hydropower project, the second hydropower plant to be opened since November 2009, when the 300-MW Tekezé project began operations.... […]
  • Plant Efficiency: Begin with the Right Definitions February 1, 2010
    The race is on to claim the title of "most efficient coal-fired power plant" on the planet. However, it’s tricky identifying finalists because of the widespread misuse of the term "efficiency" and all those nagging assumptions. Let’s first establish clear definitions and then identify the title contenders.... […]
Sedo - Buy and Sell Domain Names and Websites project info: lakho.com Statistics for project lakho.com etracker® web controlling instead of log file analysis